This Is How the US-Built Pier to Bring Aid to Gaza Worked — Or Not

The image provided by US Central Command, shows US Army soldiers assigned to the 7th Transportation Brigade (Expeditionary), US Navy sailors assigned to Amphibious Construction Battalion 1, and Israel Defense Forces placing the Trident Pier on the coast of Gaza Strip on May 16, 2024. (US Central Command via AP)
The image provided by US Central Command, shows US Army soldiers assigned to the 7th Transportation Brigade (Expeditionary), US Navy sailors assigned to Amphibious Construction Battalion 1, and Israel Defense Forces placing the Trident Pier on the coast of Gaza Strip on May 16, 2024. (US Central Command via AP)
TT

This Is How the US-Built Pier to Bring Aid to Gaza Worked — Or Not

The image provided by US Central Command, shows US Army soldiers assigned to the 7th Transportation Brigade (Expeditionary), US Navy sailors assigned to Amphibious Construction Battalion 1, and Israel Defense Forces placing the Trident Pier on the coast of Gaza Strip on May 16, 2024. (US Central Command via AP)
The image provided by US Central Command, shows US Army soldiers assigned to the 7th Transportation Brigade (Expeditionary), US Navy sailors assigned to Amphibious Construction Battalion 1, and Israel Defense Forces placing the Trident Pier on the coast of Gaza Strip on May 16, 2024. (US Central Command via AP)

The US military's pier to get humanitarian aid into Gaza has come to an end after a series of problems.

The pier was pulled from the Gaza shore on June 28 due to rough seas, and bad weather prevented troops from reinstalling it. Now, it's being dismantled and brought home.

Vice Adm. Brad Cooper, deputy commander at US Central Command, announced the end of the mission, saying the pier achieved its intended effect. And he said the Israeli port at Ashdod is a more sustainable option for aid delivery and will now be used instead.

Humanitarian groups stopped distributing supplies that arrived by sea on June 9 due to security concerns and never started again. Contractors hired by the World Food Program have removed aid that piled up onshore for distribution to starving Palestinians.

It's been a long and difficult road for the pier, which has been battered by weather and troubled by security problems. It also managed to bring tons of food and other supplies to starving Palestinians. Here's a timeline of the pier:

March: Announcement and prep MARCH 7: President Joe Biden announces his plan for the US military to build a pier during his State of the Union address.

“Tonight, I’m directing the US military to lead an emergency mission to establish a temporary pier in the Mediterranean on the coast of Gaza that can receive large shipments carrying food, water, medicine and temporary shelters,” he said.

But even in those first few moments, he noted the pier would increase the amount of humanitarian aid getting into Gaza but that Israel “must do its part” and let more aid in.

MARCH 8: Maj. Gen. Pat Ryder, Pentagon spokesman, tells reporters it will take “up to 60 days” to deploy the forces and build the project.

MARCH 12: Four US Army boats loaded with tons of equipment and steel pier segments leave Joint Base Langley-Eustis in Virginia and head to the Atlantic Ocean for what is expected to be a monthlong voyage to Gaza.

The brigade’s commander, Army Col. Sam Miller, warns that the transit and construction will be heavily dependent on the weather and any high seas they encounter.

LATE MARCH: US Army vessels hit high seas and rough weather as they cross the Atlantic, slowing their pace.

April: Construction and hope APRIL 1: Seven World Central Kitchen aid workers are killed in an Israeli airstrike as they travel in clearly marked vehicles on a delivery mission authorized by Israel.

The strike fuels ongoing worries about security for relief workers and prompts aid agencies to pause delivery of humanitarian assistance in Gaza.

APRIL 19: US officials confirm that the UN World Food Program has agreed to help deliver aid brought to Gaza via the maritime route once construction is done.

APRIL 25: Major construction of the port facility on the shore near Gaza City begins to take shape. The onshore site is where aid from the causeway will be delivered and given to aid agencies.

APRIL 30: Satellite photos show the US Navy ship USNS Roy P. Benavidez and Army vessels working on assembling the pier and causeway about 11 kilometers (6.8 miles) from the port on shore.

May: The pier opens ... then closes MAY 9: The US vessel Sagamore is the first ship loaded with aid to leave Cyprus and head toward Gaza and ultimately the pier. An elaborate security and inspection station has been built in Cyprus to screen the aid coming from a number of countries.

MAY 16: Well past the 60-day target time, the construction and assembly of the pier off the Gaza coast and the causeway attached to the shoreline are finished after more than a week of weather and other delays.

MAY 17: The first trucks carrying aid for the Gaza Strip roll down the newly built pier and into the secure area on shore, where they will be unloaded and the cargo distributed to aid agencies for delivery by truck into Gaza.

May 18: Crowds of desperate Palestinians overrun a convoy of aid trucks coming from the pier, stripping the cargo from 11 of the 16 vehicles before they reach a UN warehouse for distribution.

May 19-20: The first food from the pier — a limited number of high-nutrition biscuits — reaches people in need in central Gaza, according to the World Food Program.

Aid organizations suspend deliveries from the pier for two days while the US works with Israel to open alternate land routes from the pier and improve security.

MAY 24: So far, a bit more than 1,000 metric tons of aid has been delivered to Gaza via the US-built pier, and USAID later says all of it has been distributed within Gaza.

MAY 25: High winds and heavy seas damage the pier and cause four US Army vessels operating there to become beached, injuring three service members, including one who is in critical condition.

Two vessels went aground in Gaza near the base of the pier and two went aground near Ashkelon in Israel.

MAY 28: Large portions of the causeway were pulled from the beach and moved to an Israeli port for repairs. The base of the causeway remains at the Gaza shore.

June: Big crises for the pier JUNE 7: The damaged causeway was rebuilt and reconnected to the beach in Gaza.

JUNE 8: The US military announced that deliveries resumed off the repaired and reinstalled dock.

The same day, Israel rescued four hostages taken by Hamas during the Oct. 7 attacks in an operation that killed 270 Palestinians.

JUNE 9: World Food Program chief Cindy McCain announced a “pause” in cooperation with the US pier during a TV interview, citing the previous day’s “incident” and the rocketing of two WFP warehouses that injured a staffer.

JUNE 10: WFP said the UN would conduct a security review to assess the safety of its staff in handling aid deliveries from the pier. In the meantime, the US military said it would stockpile aid shipments on a secure beach in Gaza.

Ryder, the Pentagon spokesman, said no aspect of the pier or its equipment had been used in Israel's rescue operation. The Pentagon says an area south of the pier was used for the return of the freed hostages back to Israel.

JUNE 14: The pier was detached from the beach in Gaza to prevent damage during rough seas and allow the military to reattach it more quickly later, US officials said.

JUNE 19: The pier was re-anchored in Gaza and more than 656 metric tons, or 1.4 million pounds, of aid was delivered in the hours after it resumed operations, Ryder said.

Aid agencies, however, did not restart their distribution of the aid, so workers have been storing it in the secure area.

JUNE 28: The pier is removed due to weather, and the US is considering not putting it back unless aid begins heading again to Palestinians in need, several US officials said.

July: End of the line JULY 16: Israeli Defense Minister Yoav Gallant says Israel will soon replace the US military pier with a dedicated facility for aid delivery called Pier 28 at the port of Ashdod. He did not say when it would begin operating.

JULY 17: The Defense Department formally announces the pier will be dismantled and brought home. Altogether, the military moved nearly 20 million pounds of aid onto the Gaza shore in what officials said was the “largest volume of humanitarian assistance” ever delivered into the Middle East.



Gazans’ Daily Struggle for Water After Deadly Israeli Strike

 Palestinians wait for donated food at a community kitchen in Gaza City, in the northern Gaza Strip, Monday, July 14, 2025. (AP)
Palestinians wait for donated food at a community kitchen in Gaza City, in the northern Gaza Strip, Monday, July 14, 2025. (AP)
TT

Gazans’ Daily Struggle for Water After Deadly Israeli Strike

 Palestinians wait for donated food at a community kitchen in Gaza City, in the northern Gaza Strip, Monday, July 14, 2025. (AP)
Palestinians wait for donated food at a community kitchen in Gaza City, in the northern Gaza Strip, Monday, July 14, 2025. (AP)

The al-Manasra family rarely get enough water for both drinking and washing after their daily trudge to a Gaza distribution point like the one where eight people were killed on Sunday in a strike that Israel's military said had missed its target.

Living in a tent camp by the ruins of a smashed concrete building in Gaza City, the family say their children are already suffering from diarrhea and skin maladies and from the lack of clean water, and they fear worse to come.

"There's no water, our children have been infected with scabies, there are no hospitals to go to and no medications," said Akram Manasra, 51.

He had set off on Monday for a local water tap with three of his daughters, each of them carrying two heavy plastic containers in Gaza's blazing summer heat, but they only managed to fill two - barely enough for the family of 10.

Gaza's lack of clean water after 21 months of war and four months of Israeli blockade is already having "devastating impacts on public health" the United Nations humanitarian agency OCHA said in a report this month.

For people queuing at a water distribution point on Sunday it was fatal. A missile that Israel said had targeted fighters but malfunctioned hit a queue of people waiting to collect water at the Nuseirat refugee camp.

Israel's blockade of fuel along with the difficulty in accessing wells and desalination plants in zones controlled by the Israeli military is severely constraining water, sanitation and hygiene services according to OCHA.

Fuel shortages have also hit waste and sewage services, risking more contamination of the tiny, crowded territory's dwindling water supply, and diseases causing diarrhea and jaundice are spreading among people crammed into shelters and weakened by hunger.

"If electricity was allowed to desalination plants the problem of a lethal lack of water, which is what's becoming the situation now in Gaza, would be changed within 24 hours," said James Elder, the spokesperson for the UN's children's agency UNICEF.

"What possible reason can there be for denying of a legitimate amount of water that a family needs?" he added.

COGAT, the Israeli military aid coordination agency, did not immediately respond to a request for comment.

Last week, an Israeli military official said that Israel was allowing sufficient fuel into Gaza but that its distribution around the enclave was not under Israel's purview.

THIRSTY AND DIRTY

For the Manasra family, like others in Gaza, the daily toil of finding water is exhausting and often fruitless.

Inside their tent the family tries to maintain hygiene by sweeping. But there is no water for proper cleaning and sometimes they are unable to wash dishes from their meager meals for several days at a time.

Manasra sat in the tent and showed how one of his young daughters had angry red marks across her back from what he said a doctor had told them was a skin infection caused by the lack of clean water.

They maintain a strict regimen of water use by priority.

After pouring their two containers of water from the distribution point into a broken plastic water butt by their tent, they use it to clean themselves from the tap, using their hands to spoon it over their heads and bodies.

Water that runs off into the basin underneath is then used for dishes and after that - now grey and dirty - for clothes.

"How is this going to be enough for 10 people? For the showering, washing, dish washing, and the washing of the covers. It's been three months; we haven't washed the covers, and the weather is hot," Manasra said.

His wife, Umm Khaled, sat washing clothes in a tiny puddle of water at the bottom of a bucket - all that was left after the more urgent requirements of drinking and cooking.

"My daughter was very sick from the heat rash and the scabies. I went to several doctors for her and they prescribed many medications. Two of my children yesterday, one had diarrhea and vomiting and the other had fever and infections from the dirty water," she said.